A frame order has six stages. Most delays come from two of them: a drawing that changes after the material is cut, and a payment that lands after the vessel is booked.

Steel sections, mill hall — XinYonSen
Steel sections, mill hallTianjin mill
01

Enquiry

You send the eleven inputs. We reply with questions if any of the four price drivers is missing.

02

Quotation

Price, weight per m², loading plan, lead time, terms. Assumptions listed separately.

03

Drawing approval

We issue a member schedule and a punching drawing. Nothing is cut before you approve in writing.

04

Deposit and production

Deposit per the agreed terms; material is allocated and production scheduled.

05

Inspection

In-house check, plus third-party if you appoint one. Photos and documents issued.

06

Loading and documents

Loading plan executed, container sealed, documents couriered and emailed.

Where the time goes

Typical stage durations
StageDurationDepends on
Quotation3–5 working daysCompleteness of inputs
Drawing2–4 days after quotationYour approval speed
Production20–28 daysQuantity, coating process, season
Inspection1–2 daysInspector availability
Loading1–2 daysVessel schedule

Hot-dip adds days to production; it is a separate process, not a step in the line.

What can move a date

  • A drawing change after material is cut — the most expensive delay.
  • A payment that arrives after the vessel booking — the container is rolled.
  • A coating change from pre-galvanised to hot-dip — re-sequencing, not just re-pricing.
  • A quantity change under 5 t — the mill may not schedule a small heat.

Our commitment

We state a date range in the quotation, not a single date, and we tell you when a stage slips rather than at the end. If a vessel is missed we will say so and propose the next one.